8.1 SAP Process Audit Checklist


BS - Process Audit Checklist

List of Checkpoints

S.No.

CheckPoint

Phase

Process Area

Project Preparation

Project Initiation

1

Is there a Reviewed and approved project initiation document ( Contract / MCA / PO) existing?

Project Preparation

Project Management

2

Have the deliverables, scope & acceptance criteria defined clearly & agreed by the customer?

Project Preparation

Project Management

3

Have the responsibilities of customer defined & agreed with the customer?

Project Preparation

Project Management

4

Has the contract review done by SM/ LOB Head / SBU Head with Commercials & Marketing?

Project Preparation

Project Management

5

Did a handover take place from marketing to delivery and all necessary documents available?

Project Preparation

Project Management

6

Is there a PQM identified for the project?

Project Preparation

Project Management

7

Has the project initiation communicated to PM, PQM & the support teams( Marketing, Commercial, P& Q, HR, Sys admin,Livelink, Basis, ABAP, Remedy as applicable / all stakeholders)?

Project Preparation

Project Management

8

Has the project created in Livelink ( Can be ensured during project initiation communication)?

Project Preparation

Project Management

9

Has the contract reviewed & clarifications taken from SM/ LOB Head / SBU Head, Commercials, Customer & Account Manager?

Project Preparation

Project Management

10

Is the PM / PQM trained on QMS? If not training requirement given?

Project Preparation

Project Management

11

Has the Project Repository checked for similar project documents?

Project Preparation

Project Management

12

Have the SM/ LOB Head, PM, PQM registered in the QMS Portal with the respective roles?

Project Preparation

Project Management

13

Have all the team Members registered in the QMS Portal?

Project Preparation

Project Management

14

Is the Risk Escalation Level available from proposal team?

Project Preparation

Project Management

15

Has the scope, customer objective, customer responsibilities, project standards etc. discussed with the customer and agreed?

Project Preparation

Project Management

16

Has the Project Charter prepared with the right template and complete as applicable?

Project Preparation

Project Management

17

Is project Charter reviewed & approved (Review Records should be available) by SM/ LOB Head as applicable?

Project Preparation

Project Management

18

Has the Project Charter forwarded to customer for approval as applicable?

Project Preparation

Project Management

19

Are responsibilities of the Customer clearly defined and agreed with customer?

Project Preparation

Project Management

20

Is there a clearly defined SLA / monitoring mechanism agreed with the customer ?

Project Preparation

Project Management

21

Has the project registered in the QMS Portal with all relevant information & status as "Ramp Up"?

Project Preparation

Project Management

22

Has the project standards finalized?

Project Preparation

Project Management

Project Plan Preparation

23

Is Project Quality Plan developed with project process, tailoring and necessary goals (metrics) defined using right template and all sections completely defined?

Project Preparation

Project Management

24

Are reviews identified as an SQA activity for each work product?

Project Preparation

Project Management

25

Deviations if any is agreed with TC?

Project Preparation

Project Management

26

Has the estimation done based on the inputs from contract as well as the scope identified during Project Charter preparation?

Project Preparation

Project Management

27

Is Project Plan developed using right template and all sections completely defined?

Project Preparation

Project Management

28

Does project plan scopes for Stakeholders?

Project Preparation

Project Management

29

Does project plan scopes Responsibilities for TC and PQM

Project Preparation

Project Management

30

Does project plan scopes Responsibilities for Commercial and Sales / Account Management as applicable?

Project Preparation

Project Management

31

Does project plan scope identifies the Critical Dependencies / Success Factors (e.g. critical facility, test groups etc) ?

Project Preparation

Project Management

32

Does project plan scopes Identification of standard tools to be used in the project, even if customer doesn’t specify the tool?

Project Preparation

Project Management

33

Does project plan scopes Identification of reused components for the project?

Project Preparation

Project Management

34

Does project plan scopes Evaluation of needed granularity for tracking (effort, schedule, cost and quality) to meet customer requirements?

Project Preparation

Project Management

35

Does project plan use standard method of estimation e.g. Delphi ?

Project Preparation

Project Management

36

Is “Lesson Learnt” identified as an "end deliverable of project" ?

Project Preparation

Project Management

37

Has the latest QMS documents to be used in the projects identified & documented?

Project Preparation

Project Management

38

Is the Risk Management being done in the project?

Project Preparation

Project Management

39

Has the Risk Escalation Level revisited & updated for the delivery phase?

Project Preparation

Project Management

40

Whether the sources of risks are categorized, impact of the risk is estimated & prioratized? (Impact on Cost, Quality, Schedule etc). Risk should not be generic

Project Preparation

Project Management

41

Has the project organization been established on the basis of the project structure and are the organizational plans (internal/external (for customers and partners)) complete and represented in a clear format?

Project Preparation

Project Management

42

Have the distribution lists been determined and documented to ensure the flow of information?

Project Preparation

Project Management

43

Is a risk mitigation/contingency plan prepared for identified risks?

Project Preparation

Project Management

44

Is there a mechanism to share risk status with affected parties.

Project Preparation

Project Management

45

Is Mechanism of status review (e.g. Project Report, MIS etc) items with higher management in place ?

Project Preparation

Project Management

46

Are the project goals based on SBU/Organization goals? Whether reasons documented if deviating from the SBU/Org goals.

Project Preparation

Project Management

47

Are project team members aware of the deviated process and process is well understood.

Project Preparation

Project Management

48

Does the PES / PSR include the monitoring of all life cycle activities planned in the Project?

Project Preparation

Project Management

49

Are the skills & knowledge needed for each team member (functional and technical) identified at the project level?

Project Preparation

Project Management

50

Is the training schedule(name of the participant, when the training is needed etc…) available?

Project Preparation

Project Management

51

Does the training schedule cover mode of training (self-study, on-job training, classroom training etc.)

Project Preparation

Project Management

52

Are training delivered as planned?

Project Preparation

Project Management

53

Is mentoring done as identified in the Training Plan?

Project Preparation

Project Management

54

Are the re-planning criteria set?

Project Preparation

Project Management

55

Is there any Internal escalation mechanism established? (Should include issue resolution and management among affected parties etc)

Project Preparation

Project Management

56

Is Service Planning in terms of Manpower (identification of delivery/operation manager) done?

Project Preparation

Project Management

57

Does an Escalation mechanism exist with Customer and /or Subcontracting agency? Is that documented and approved?

Project Preparation

Project Management

58

Is Service Planning in terms of Resources - Hardware / software done?

Project Preparation

Project Management

59

Does project scopes Handling of customer supplied products

Project Preparation

Project Management

60

Is the Draft Project Plan forwarded to PQM, TC & SM/ LOB Head for Review?

Project Preparation

Project Management

61

Is Configuration Management Plan sections is completely defined, reviewed and approved?

Project Preparation

Project Management

62

Is there a plan defined for the Configuration Audit?

Project Preparation

Project Management

63

Is project monitored and tracked regularly as per plan with the team? Verify Closure of previous Audit findings

Project Preparation

Project Management

64

Are responsibilities for Change Management defined and members identified?

Project Preparation

Project Management

65

Are the Project baselines identified?

Project Preparation

Project Management

66

Is there a backup procedure for work products?

Project Preparation

Project Management

67

Is release management defined?

Project Preparation

Project Management

68

Has a change order strategy determined?

Project Preparation

Project Management

69

Has the change order procedure agreed upon with the business partners (principal, suppliers etc.), documented and implemented?

Project Preparation

Project Management

70

Has a claims strategy determined, and is the procedure for this documented?

Project Preparation

Project Management

PES Planning

71

Has the start PES presentation prepared?

Project Preparation

Project Management

72

Has the invitation for start PES forwarded to all support teams?

Project Preparation

Project Management

73

Has the start PES Meeting conducted as scheduled?

Project Preparation

Project Management

74

Has the clarifications taken from all stakeholders?

Project Preparation

Project Management

75

Has Project plan commitments discussed and agreed with Mandatory participants of the Start PES meeting?

Project Preparation

Project Management

76

Has Project plan commitments discussed and agreed with Project Team?

Project Preparation

Project Management

77

Has the PES decision sheet forwarded to all attended the meeting/ invited?

Project Preparation

Project Management

Project Preparation Phase Closure

78

Has the Project Plan updated based on the feedback in the meeting?

Project Preparation

Project Management

79

Has the Project briefing (Project Overview & Process Overview) done to all team members?

Project Preparation

Project Management

80

Has the Project Charter approved by the client as applicable?

Project Preparation

Project Management

81

Has the re-scheduling of Project Preparation phase done in case of anticipated delay in Project Charter approval (Next Phase can be started parallelly)?

Project Preparation

Project Management

82

Has the project plan walkthrough scheduled & communicated to reviewers?

Project Preparation

Project Management

83

Has the walkthrough of Project Plan done?

Project Preparation

Project Management

84

Has the final Review observations documented?

Project Preparation

Project Management

85

Has the open points verified by PQM for closure?

Project Preparation

Project Management

86

Is there a documented approval available for Project Plan?

Project Preparation

Project Management

87

Has the Project Plan released (after uploading in Livelink, communicate through livelink notification or through e-mail)?

Project Preparation

Project Management

88

Has the Project Kick off meeting done with the customer?

Project Preparation

Project Management

89

Has the Kick off meeting minutes forwarded to all attended the meeting?

Project Preparation

Project Management

90

Has all the activities scheduled in the project preparation phase completed?

Project Preparation

Project Management

91

Has the Project Status in QMS portal set to "Live"?

Project Preparation

Project Management

92

Has the approved documents uploaded in Livelink?

Project Preparation

Project Management

93

Has the configuration audit conducted as planned?

Project Preparation

Project Management

Project Monitoring - Monthly

94

Is QMS Intranet updated with the latest project information?

All Phases after Project Preparation

Project Management

95

Is there any evidence of re-plan when the re-planning criterion is met?

All Phases after Project Preparation

Project Management

96

Is the revised project plan reviewed & released after closure of review observations?

All Phases after Project Preparation

Project Management

97

Is project monitored and tracked regularly as per plan with the team? Verify Monthly PR (completeness etc)

All Phases after Project Preparation

Project Management

98

Is th escalation mechanism followed? (Should include issue resolution and management among affected parties etc)

All Phases after Project Preparation

Project Management

99

Has Project plan changes discussed and agreed with Mandatory participants of the Start PES meeting

All Phases after Project Preparation

Project Management

100

Has Project plan changes if any discussed and agreed with Project Team

All Phases after Project Preparation

Project Management

101

Is compliance to agreed SLA / Commitments with the customer tracked ?

All Phases after Project Preparation

Project Management

102

Is Service Planning in terms of Resources - Hardware / software done and being tracked ?

All Phases after Project Preparation

Project Management

103

Is Service Planning in terms of Manpower done and being tracked?

All Phases after Project Preparation

Project Management

104

Are internal (project team) and, if stipulated in the contract, external (e.g. project steering committee with customers) project status meetings organized and held? MOMs

All Phases after Project Preparation

Project Management

105

Is project monitored and tracked regularly as per plan with the team? Verify Issues, open action items (including RRB, Issue Logs, PR, PES Decision sheet, etc) till closure

All Phases after Project Preparation

Project Management

106

Is project monitored and tracked regularly as per plan with the team? Verify On-site work/team

All Phases after Project Preparation

Project Management

107

Is project monitored and tracked regularly as per plan with the team? Verify Critical dependencies / Critical Success Factors

All Phases after Project Preparation

Project Management

108

Is project monitored and tracked regularly as per plan with the team? Verify Closure of previous Audit findings

All Phases after Project Preparation

Project Management

109

Are projected values of the efforts being used while tracking and re-planning

All Phases after Project Preparation

Project Management

110

Is project using control charts for process monitoring and action plan documented for outliers

All Phases after Project Preparation

Project Management

111

Are improvements in trend tracked and recorded?

All Phases after Project Preparation

Project Management

112

Are all affected parties participating during the project tracking?

All Phases after Project Preparation

Project Management

113

Is actual impact vs. planned impact tracked, on occurence of actual risk?

All Phases after Project Preparation

Project Management

114

Has the Timesheet filled in for the month?

All Phases after Project Preparation

Project Management

115

Has the Project Report for the month is prepared? ( As on 20th)

All Phases after Project Preparation

Project Management

116

Has the Project Report reviewed by PQM for correctness & completeness of the contents & improvement recommendations provided?

All Phases after Project Preparation

Project Management

117

Has Project Report reviewed & recommendations given by SM/ LOB Head & TC?

All Phases after Project Preparation

Project Management

118

Has the PSR scheduled & informed to all concerned?

All Phases after Project Preparation

Project Management

119

Has the PSR conducted as scheduled?

All Phases after Project Preparation

Project Management

120

Has the PSR conducted covers all points given in PSR Checklist?

All Phases after Project Preparation

Project Management

121

Has the root cause identified for the deviations from planned & action planned?

All Phases after Project Preparation

Project Management

122

Has the PSR released to all participants?

All Phases after Project Preparation

Project Management

123

Has the approved documents uploaded in Livelink?

All Phases after Project Preparation

Project Management

124

Is Change Management implemented as defined?

All Phases after Project Preparation

Project Management

125

Is the defined Change Management process followed for changes raised by team members.

All Phases after Project Preparation

Project Management

126

Has the configuration audit conducted as planned?

All Phases after Project Preparation

Project Management

127

Is implementation of QA activities as per defined plan?

All Phases after Project Preparation

Project Management

128

Has the completed Process Audit Checklist forwarded to TC? (10th of every month)

All Phases after Project Preparation

Project Management

129

Are the changes to Project baselines tracked?

All Phases after Project Preparation

Project Management

130

Is the backup procedure for work products implemented?

All Phases after Project Preparation

Project Management

131

Is release management implemented?

All Phases after Project Preparation

Project Management

132

Has a change order strategy determined?

All Phases after Project Preparation

Project Management

133

Has the change order procedure agreed upon with the business partners (principal, suppliers etc.), documented and implemented?

All Phases after Project Preparation

Project Management

134

Are changes to the contract (claims) identified, recorded and documented consistently?

All Phases after Project Preparation

Project Management

135

Are the changes to the contract(claims) processed correctly and asserted / defended fairly but persistently?

All Phases after Project Preparation

Project Management

136

Are major defects (from reviews and testing) analyzed and corrective and preventive actions planned and taken

All Phases after Project Preparation

Project Management

Project Closure

Go-Live / One month before Project Completion Date

137

Has the Acceptance Certificate & Feedback Form forwarded to customer?

During Closure

Project Management

138

Has the Go-Live Sign off received from customer (for Implementation / Upgrade Projects)?

During Closure

Project Management

139

Bills forwarded for payment as per contract terms?

During Closure

Project Management

140

Has all activities completed in the project as given in the project plan?

During Closure

Project Management

Post Go-Live & Support / Project Completion

141

Has the Acceptance Certificate & Feedback of Project received from customer?

During Closure

Project Management

142

Has the copy of Customer Feedback forwarded to TC?

During Closure

Project Management

143

All bills settled or any invoice pending payment?

During Closure

Project Management

144

Has the project end Project Report prepared ?

During Closure

Project Management

145

Has the lessons learnt from the project documented?

During Closure

Project Management

146

Has the End PES presentation prepared?

During Closure

Project Management

147

Has the invitation for End PES forwarded to all support teams?

During Closure

Project Management

148

Has the End PES Meeting conducted as scheduled?

During Closure

Project Management

149

Has the PES decision sheet forwarded to all attended the meeting/ invited?

During Closure

Project Management

150

Has the Skills Inventory Database (Resume) of the team members updated?

During Closure

Project Management

151

All documentation uploaded in Repository (Livelink) for safe keeping of records?

During Closure

Project Management

152

Final Configuration audit is conducted for the project?

During Closure

Project Management

153

Has all Reusable& Best Practices handed over to / shared with SEPG?

During Closure

Project Management

154

Has all Hardware used in project released?

During Closure

Project Management

155

Has Software if any used in project removed?

During Closure

Project Management

156

Has the Training Materials & Records handed over to Training Coordinator?

During Closure

Project Management

157

Have all personnel in project released after completing appraisal and handing over the appraisal sheets to HR?

During Closure

Project Management

158

Has the Project documents (PP, End PES documents, Lessons Learnt) are uploaded in the QMS Portal?

During Closure

Project Management

159

Has the Project Status set to "Completed" in the QMS Portal?

During Closure

Project Management

160

Has the Risk Database updated / shared with SEPG?

During Closure

Project Management

161

Has Livelink access for the Project Team updated?

During Closure

Project Management

162

Has the completed Process Audit Checklist forwarded to TC?

During Closure

Project Management

Engineering Activities

163

Are Gaps analysed (Implementation projects)?

BBP

Engineering

164

Are projects requirements agreed with the customer and evidence of agreement is available (sign off etc.)

BBP

Engineering

165

Is Tracebility Matrix maintained ?

All Phases after Project Preparation

Engineering

166

Is the responsibility of the requirement management/approval defined?

All Phases after Project Preparation

Engineering

167

Is there established tracking mechanism of status of the requirements at each stage (analysis, development, approval and changes in requirement) of requirement engineering

All Phases after Project Preparation

Engineering

168

Are all the agreed deliverables (e.g. BBP / Business Specification, FS, TS, Customization Document etc) produced as per the defined process? (Make sure on sample basis that the output is consistent with the input)

All Phases after Project Preparation

Engineering

169

Has the sign off on the deliverables received as defined in the projectplan?

All Phases after Project Preparation

Engineering

170

Is project using formal review methods?

All Phases after Project Preparation

Engineering

171

Are the review methods for the work products selected as per the defined procedure and are evident in the plan

All Phases after Project Preparation

Engineering

172

Is operation concepts and scenario documented

Realization

Engineering

173

Is there a coding standard defined and verified its implementation?

Realization

Engineering

174

Are documents and code reviews are performed?

Realization

Engineering

175

Are the Test activities planned (as a part of project plan or separate test plan), reviewed and approved?

Realization

Engineering

176

Is test coverage for the project defined?

Realization

Engineering

177

If test plan is developed separately, verify if Test Plan is developed using right template and all sections completely defined

Realization

Engineering

178

Is Test environment planned and reviewed with the development team

Realization

Engineering

179

Is Testing done as per plan

Realization

Engineering

180

Whether Test documents and Test code reviews are performed?

Realization

Engineering

181

Is test report for all the testing done available

Realization

Engineering

183

Is live run performed (Implementation projects)?

Go-Live & Post Go-Live Support

Engineering

184

Are the bugs recorded?

All Phases after Project Preparation

Engineering

185

Are the recorded bugs tracked to closure?

All Phases after Project Preparation

Engineering

3 comments:

Unknown said...

Extraordinary blog. you put Good stuff. All the themes were clarified briefly. Thank you so much for sharing that valuable blog. Inventory Audit
Internal Audit
Vendor Reconciliation

isabella said...
This comment has been removed by the author.
Sherin infanta said...

Good job in presenting the correct content with the clear explanation. The content looks real with valid information. Good Work... Duplicate Payment Review
Continuous Monitoring
Vendor Audit
Duplicate Payment Recovery

link us...

For Visitors

if you want to publish or Add something on ERP, SAP , SAP FUNCTIONAL, SAP ABAP then mail us along with your email-id. contain must be yours

email-id :- avinashkr_raj@yahoo.com(any email)

email-id :- avinaskr_raj.abap@blogger.com ( use only gmail)